Program Status Report

Write program status reports that surface risks and decisions, not just progress — with executive summaries, workstream tracking, dependency maps, and escalation frameworks.

status-reportprogram-managementreportingriskstracking

Works well with agents

Engineering Manager AgentProject Manager AgentTechnical Program Manager Agent

Works well with skills

Ticket Writing
$ npx skills add The-AI-Directory-Company/(…) --skill program-status-report
program-status-report/
    • platform-migration-week-6.md4.0 KB
  • SKILL.md6.6 KB
program-status-report/examples/platform-migration-week-6.md
platform-migration-week-6.md
Markdown
1# Program Status Report: Platform Migration — Week 6
2 
3```
4Program: Legacy Platform → Cloud-Native Migration | Period: Mar 9-20, 2026
5Overall Status: YELLOW | Author: D. Okafor
6Distribution: Steering Committee, VP Engineering, VP Product
7```
8 
9## Executive Summary
10 
11The migration program is on track for the June 30 production cutover, but the API Gateway workstream has slipped to YELLOW due to an unresolved authentication integration with the new identity provider. Data migration and frontend rebuild remain on schedule. If the identity provider issue is not resolved by March 27, the end-to-end staging milestone (April 10) is at risk, which would compress the 4-week soak period before cutover. A decision is needed this week on whether to proceed with the vendor integration or switch to an in-house OAuth2 implementation.
12 
13## Status by Workstream
14 
15| Workstream | Owner | Status | Progress This Period | Next Milestone | Risk |
16|---|---|---|---|---|---|
17| Data migration | @r.tanaka | GREEN | Migrated 4/6 schemas; referential integrity tests passing | Schema 5 (Billing) by Mar 27 | None |
18| API gateway | @s.mehta | YELLOW | 8/12 endpoints migrated; auth integration blocked 5 days | Auth integration complete by Mar 27 | IdP vendor unresponsive — see Risks |
19| Frontend rebuild | @l.vasquez | GREEN | Dashboard and settings pages shipped to staging | Reports page by Apr 3 | None |
20| Observability | @k.wright | GREEN | Datadog dashboards deployed; alerting rules migrated | Load test baseline by Apr 7 | None |
21| Data validation | @r.tanaka | GREEN | Automated diff pipeline running on schemas 1-3 | Schema 4 diff validation by Mar 25 | None |
22 
23## Milestones
24 
25```
261. Auth integration complete — Mar 27 — @s.mehta — Medium (blocked on IdP vendor)
272. Schema 5 migration — Mar 27 — @r.tanaka — High
283. Schema 6 migration — Apr 3 — @r.tanaka — High
294. Reports page shipped — Apr 3 — @l.vasquez — High
305. End-to-end staging test — Apr 10 — @d.okafor — Medium (depends on #1)
316. Production cutover — Jun 30 — @d.okafor — Medium (depends on staging soak period)
32```
33 
34## Risks and Mitigations
35 
36```
37Risk: Identity provider vendor has not responded to SAML configuration questions in 7 business days.
38Impact: API gateway auth integration delayed 1-2 weeks, compressing staging soak from 4 weeks to 2.
39Likelihood: Medium
40Mitigation: Escalated to vendor account manager on Mar 16. Engineering has spiked an in-house
41 OAuth2 implementation (estimated 8 days of effort) as a fallback.
42Owner: @s.mehta
43Escalation trigger: No vendor response by Mar 27 — will recommend switching to in-house OAuth2,
44 requiring VP Engineering approval for the additional engineering investment.
45```
46 
47```
48Risk: Billing schema (Schema 5) contains 14M rows with inconsistent currency formatting.
49Impact: Migration may require a data cleaning step adding 3-5 days.
50Likelihood: Low
51Mitigation: @r.tanaka is running a profiling pass this week to quantify the scope. Cleaning
52 script is drafted and ready to execute if needed.
53Owner: @r.tanaka
54Escalation trigger: If >5% of rows require cleaning, migration timeline extends past Mar 27.
55```
56 
57## Decisions Needed
58 
59**Decision 1: Identity provider approach**
60- **Option A**: Continue waiting for vendor response. Risk: further delay.
61- **Option B**: Switch to in-house OAuth2 implementation. Cost: 8 engineering-days, ~$0 licensing vs. $24K/year vendor cost saved.
62- **Recommendation**: Set a hard deadline of Mar 27 for vendor response. If no resolution, proceed with Option B.
63- **Deadline for decision**: Mar 27
64 
65## Key Metrics
66 
67| Metric | Current | Target | Trend |
68|--------|---------|--------|-------|
69| Endpoints migrated | 8/12 (67%) | 12/12 by Apr 3 | On pace (was 5/12 last period) |
70| Schemas migrated | 4/6 (67%) | 6/6 by Apr 3 | On pace |
71| Staging test coverage | 74% | >90% by Apr 10 | Up from 61% |
72| Open blockers | 1 | 0 | Unchanged from last period |
73| Budget spent | $142K of $310K (46%) | <$310K | On track |
74 